Sierra Construction is nearing completion of this 4-story office building (for training and various banking departments) for Frontier Bank in Everett. The first floor of the building is below-grade with three additional floors above. The structure is a combination of structural steel and steel joist with slab-on-metal decking and includes structural cast-in-place concrete cores for stairwells and elevator shaft. The skin/envelope is metal-stud framed walls with CMU-brick veneer and punched storefront openings. All floors will be fully built-out and finished with standard office finishes. This project is being performed adjacent to the active and operating bank office building and includes a third-story connection to that office building. The building is scheduled to be completed in February, 2008.