Project Completion: Bridge Point I-5, Phase 2

BPI5 (3)

Phase 2 of Bridge Industrials I-5 development in Milton, WA, which included the construction of three speculative industrial buildings, has been completed.

Building 2:

  • 461,277 square feet
  • 70 dock-high doors
  • 2 at-grade doors
  • 40' clear height


Building 3:

  • 330,449 square feet
  • 56 dock-high doors
  • 2 at-grade doors
  • 36' clear height


Building 4:

  • 124,799 square feet
  • 18 dock-high doors
  • 2 at-grade doors
  • 34' clear height


Each building also included approximately 3,000 square foot speculative office tenant improvements. 

Due to the slope of the 62 acre site, sitework also included 56,000 square feet of soil nail and 35,000 square feet of MSE retaining walls. The first phase of the 118 acre total development, which included site infrastructure and the construction of Building 1, was completed in 2023. For more information on this project, you can visit https://bridgepointi5seattle.com/


Sierra Construction Team:

Andy Bley, Senior Project Manager
Evan Heeringa, Project Manager
Ryan McCarty, Project Engineer
Taylor Ebersole, Project Engineer
Ulises Gonzalez, Superintendent
Harrison Wiese, Foreman
May Jensen, Project Administrator

Project Team:

Client: Bridge Industrial
Architect: NELSON
Engineers: Barghausen, AHBL & Terra Associates
General Contractor: Sierra Construction
Subcontractors include: Lloyd Enterprises, RE Sides, Miles Resources, Carmona, K Kenny, Snell Crane, Brundage Bone, Olympic Iron Works, Panelized, A-1 Daylight, CanAm Coatings, Cascade Door, DLT & Ambiance Coatings

On the Subject

Cook Street Apartments: Designed for the cycling centric
Project Updates
Cook Street Apartments: Designed for the cycling centric

Originally published by the Business Tribune; written by Jules Rogershttp://pamplinmedia.com/but/239-news/303486-180457-designed-for-the-cycling-centric In Por...

Continue Reading