Monthly Archives: May 2019

NEWS

20 May 2019

Amazon Troutdale wins at Oregon’s DJC TopProjects event

2019-05-20T14:11:47+00:00

Last Thursday held Oregon's DJC TopProjects awards event at the Oregon Convention Center- and Amazon Troutdale was named 2nd Place Winner in the Industrial Development of the Year category. With 97 finalists in various categories, Sierra had two projects in the running for Industrial Development of the Year; Amazon Troutdale and IPT Tualatin.   Sierra Senior Project Manager, Kristi Walz, accepting the award at Thursday's event (photo from DJC)   For more on the event, visit: http://djcoregon.com/news/2019/05/17/building-industrys-best-honored-annual-topprojects-awards/     In [...]

Amazon Troutdale wins at Oregon’s DJC TopProjects event 2019-05-20T14:11:47+00:00
20 May 2019

Project Update: Blackbird Apartments

2019-05-20T12:23:21+00:00

Crews at Blackbird Apartments recently removed the tower crane, in preparation of the final stretch towards completion. Framing was completed in April and the building is nearly tight to the weather.  Concrete decks were poured within the lower hotel units and metal framing within the lower levels is in progress.  All unit MEP rough-ins are in progress, and teams will start stocking drywall next week. Just blocks from Redmond town center, Blackbird will be five stories of wood framed residential [...]

Project Update: Blackbird Apartments 2019-05-20T12:23:21+00:00
17 May 2019

Project Update: Troutdale Lot 10

2019-05-16T12:03:23+00:00

Project teams began the first tilt for Troutdale Lot 10 this week. In total, there will be 111 wall tilt-panels and 12 dock/trash enclosure panels. This week includes picking 94 during the first tilt, and the remaining 29 on the second mobilization in June. Structural steel and roof structure are to follow the conclusion of the final tilt. This a speculative concrete tilt-up warehouse being built in Troutdale, Oregon. The project broke ground on sitework in the summer of 2018, [...]

Project Update: Troutdale Lot 10 2019-05-16T12:03:23+00:00
16 May 2019

Project Completion: First Glacier Logistics

2019-05-16T10:50:13+00:00

First Glacier Logistics Center has been completed. Work began on First Glacier Logistics in October 2018. Built with a total of 55 tilt panels, limited slab space resulted in two separate tilts to successfully close the building exterior.  This new distribution facility totals 66,000 square feet, with a 30’ clear height and sits on a 3.8 acre site. First Glacier will also feature 18 exterior dock doors, 2 drive-in doors, and over 60 parking spaces. For more information, visit First [...]

Project Completion: First Glacier Logistics 2019-05-16T10:50:13+00:00
10 May 2019

Bridge expands into Kent and Sumner

2019-05-10T09:13:40+00:00

Source: https://www.djc.com/news/re/12121565.html?action=get&id=12121565&query=bridge%20expands Bridge Development Partners has formally announced two industrial projects in Kent and Sumner. Bridge Point Kent 100 is being built on a 4.7-acre site it acquired last month for almost $5 million. The new building, at 26524 79th Ave. S., will have 97,500 square feet, with 30-foot clear heights, and 14 dock-high and two grade-level doors. Nelson is the architect, and Sierra Construction Co. is the general contractor. Construction will begin soon, and should be completed in early 2020. Shawn Childs and Andrew Stark of CBRE are leasing the property for Bridge. Bridge Point Sumner 60 will be [...]

Bridge expands into Kent and Sumner 2019-05-10T09:13:40+00:00