19Mar 2018

2017 Company Bulletin

Click to download Sierra’s 2017 Company Bulletin


8Mar 2018

Project Update: Georgetown Crossroads

The project team at Prologis’ Georgetown Crossroads took a moment to celebrate on Tuesday, as the structural steel erection on the main, three-story section of the fulfillment center had been completed.

Coastal Steel began the steel erection process in December of 2017, and was completed on March 6th. Approximately 5,000 tons of structural steel was used in the three-story building. The shell was tilted with 86 panels; the largest weighting 210,000lbs.

The project team is now in the process of completing 16, Read More >