Project Update: Marysville Corporate Center, Buildings 101-104

Marysville Corp (1)

August marks the first of two tilts for Phase 1 at the Marysville Corporate Center. The four building, speculative first phase of the development broke ground earlier this year.

  • Building 101: 55,970 square feet
  • Building 102: 63,850 square feet
  • Building 103: 73,880 square feet
  • Building 104: 73,880 square feet

All four buildings will have a 24' clear height.

Sitework included completing the infrastructure needed for both Phase 1 and Phase 2. Phase 1 is being constructed on a 15.1 acre portion of the site.



Sierra Construction Team:

Kirk MacGowan, Senior Project Manager
Mike Stout, Project Manager
Conor Cahill, Project Engineer
Tim Clark, Superintendent
Katelyn McNeely, Project Administrator

Project Team:

Owner: PacTrust
Architect: Mackenzie
Engineers: Mackenzie
General Contractor: Sierra Construction
Subcontractors include: RE Sides, State Mechanical, Taylors Excavators, TriStar Roofing, Parrott's Welding, Panelized, Coastal, Ness & Campbell Crane, & DKS

On the Subject

Panattoni starts expansion at state’s former liquor warehouse
Project Updates
Panattoni starts expansion at state’s former liquor warehouse

Panattoni Development Co. has broken ground on a 111,677-square-foot expansion to the former Washington State Liquor Control Board’s warehouse at 4401 E. Margin...

Continue Reading