Skip to main content

Project Update: Redmond Ridge, Buildings 104 & 105

RR 104 105 8-2-21 web

Buildings 104 and 105 of the Redmond Ridge industrial development are underway. Sitting adjacent to Building 113 which was completed last year, the 9.77 acre site was previously undeveloped. 

Building 105's walls were tilted in June, and will be 67,700 square feet when completed. 

Building 104 is schedule for August, and will be 52,200 square feet. 

This project is due for completion later this year. 


Sierra Construction Team:
Kirk MacGowan, Senior Project Manager
Matt Frause, Project Manager
Katelyn McNeely, Project Administrator

Project Team:
Developer: M&T Partners
Architect & Engineer: Mackenzie

On the Subject

New Project: Tacoma Screw Fulfillment
Project Updates
New Project: Tacoma Screw Fulfillment

Sitework began on the former site of Gig Harbor Athletic Club earlier this summer, making way for a new fulfillment center for Tacoma Screw Products. The 9.17...

Continue Reading