Skip to main content

Project Update: The Cubes at Troutdale

PU Troutdale

Project teams began the first tilt for Troutdale Lot 10 this week.

In total, there will be 111 wall tilt-panels and 12 dock/trash enclosure panels. This week includes picking 94 during the first tilt, and the remaining 29 on the second mobilization in June. Structural steel and roof structure are to follow the conclusion of the final tilt.

This a speculative concrete tilt-up warehouse being built in Troutdale, Oregon. The project broke ground on sitework in the summer of 2018, which involved a 5’ tall building pad surcharge that was completed and has now been removed from the site. Since the new year, the project team has been working on digging 775 aggregate piers and spread footings which will be completed this week. Five slab-on-grade pours totaling over 145,000 square feet have been completed, and the team is beginning to form tilt panels. The completed project will have 84 dock and 4 drive in doors and a 36’ clear height inside the first column line. The final building will be 349,080 square feet.

On the Subject

Project Completion: PDX9 (Project Piper)
Project Updates
Project Completion: PDX9 (Project Piper)

Amazon Troutdale (previously known as Project Piper) is a 857,470 square foot distribution center on a 74 acre site in the Reynolds Industrial Park of Troutdale...

Continue Reading