Skip to main content
Edit Page - Admin Only Control Panel - Admin Only

Project Update: Project Piper

PU Pdx9

Project Piper’s first tilt phase was completed at the end of September. 66 panels, and included the smallest panel in the building, at only 54′ tall and 73,340lbs. (yes, only)

Breaking ground spring of 2017, Project Piper will be a 857,000 square foot distribution center to occupy three previously vacant lots in the Troutdale Reynolds Industrial Park. The 74 acre site will also have 2,500 car parking spaces, 276 trailer parking spaces, and over 60 loading docks.

On the Subject

New Project: Track 6
Project Updates
New Project: Track 6

Currently under construction, Track 6 will be a new 4-story, Class-A industrial building located on the old Compton Lumber site in the middle of Seattle’s SODO...

Continue Reading