Project Completion: Portland Portal Industrial, Phase II

PC Portland POrtal

Sierra broke ground on Phase 2 of the Portland Portal Industrial Center June 2018. The 22 acre site has three buildings, totaling just under 360,000 square feet of warehouse and manufacturing space.

Located in the City of Gresham, the 22 acre development took just under 14 months to complete. Building A is 110,000 square feet with 21 dock-high doors, Building B is the smallest, at 47,000 square feet with 10 dock doors and finally the largest of the three, Building C is 203,000 square feet and has 46 dock doors. All three buildings have a 30’ clear height.

PROJECT TEAM

General Contractor: Sierra Construction

Developer: Panattoni

Leasing: Kidder Matthews and Macadam Forbes

Architect & Engineer: Mackenzie

Subcontractors:

Goodfellow Bros, LLC

A-Line Concrete Cuting

Alite Construction

Knife River Corporation

Ralph’s Concrete Pumping

Panelized Structures Inc

Weatherguard, inc

Ness & Campbell Crane, Inc

AFP Systems, Inc

Gohman Mechanical, Inc

Stewart Plumbing, Inc

Timberline Electric

On the Subject

Employee Spotlight: Ashley Metcalfe
Employee Spotlight
Employee Spotlight: Ashley Metcalfe

Ashley has been in the accounting department at Sierra for 10 years. However, she has been in construction accounting specifically since she was 19. “I’ve been...

Continue Reading