First Glacier Logistics Center has been completed.

Work began on First Glacier Logistics in October 2018. Built with a total of 55 tilt panels, limited slab space resulted in two separate tilts to successfully close the building exterior. This new distribution facility totals 66,000 square feet, with a 30’ clear height and sits on a 3.8 acre site. First Glacier will also feature 18 exterior dock doors, 2 drive-in doors, and over 60 parking spaces.

For more information, visit First Industrial

On the Subject

Project Completion: Redmond Ridge 113
Project Updates
Project Completion: Redmond Ridge 113

The largest building to-date in the Redmond Ridge Business Park, Building #113 is a 129,687 warehouse with a 24’ clear height. Sitework included the clearing of...