Project Completion: First Glacier Logistics

PC First Glacier

First Glacier Logistics Center has been completed.

Work began on First Glacier Logistics in October 2018. Built with a total of 55 tilt panels, limited slab space resulted in two separate tilts to successfully close the building exterior. This new distribution facility totals 66,000 square feet, with a 30’ clear height and sits on a 3.8 acre site. First Glacier will also feature 18 exterior dock doors, 2 drive-in doors, and over 60 parking spaces.

For more information, visit First Industrial

On the Subject

Project Completion: Frank Albert Industrial, Building B
Project Updates
Project Completion: Frank Albert Industrial, Building B

Located on a 82.78 acre site owned by the Puyallup Tribe of Indians, Building B of the Frank Albert Industrial Park was completed in February of 2025. The 138,9...

Continue Reading